When do the cones on Emmaus Church Road come down? If you've waited at the temporary signals on the Route 106 bridge over I-64 since summer 2025, VDOT has an answer for that bridge. It expects the replacement to be finished in spring 2027.
The interchange is a different story. VDOT's schedule for the Exit 211 diverging diamond project shows construction starting in spring 2027 and finishing in fall 2029. Both projects end up on the same calendar. The season the bridge work wraps up is the season the larger rebuild begins, at the same exit, on the same stretch of Route 106.
Why the Bridge Has Been One Lane Since Summer 2025
The bridge work belongs to a bigger job. VDOT's I-64 Gap Segment A widening adds one general-purpose lane in each direction over 10.7 miles, from mile marker 204.9 just west of the Bottoms Bridge exit to 215.6 just east of the New Kent Courthouse/Providence Forge exit. That takes the interstate from four lanes to six. VDOT calls it the first of three segments that will eventually widen I-64 all the way to mile marker 234 in York County. The project page lists it as under construction, with an estimated cost of $209.5 million and estimated completion in summer 2027. Shirley Contracting Company is the design-build contractor, according to a VDOT release.
The Emmaus Church Road bridge is part of that scope. VDOT's bridge replacement FAQ describes the old bridge as structurally deficient and past the point where maintenance makes sense. It also says structurally deficient does not mean unsafe to use. The bridge is being rebuilt in two halves. Phase 1 tears down and rebuilds the west half while traffic uses the east half. Phase 2 reverses that, putting traffic on the new west half while the east half comes down. VDOT's July 1, 2026 traffic alert said traffic would move to the opposite lane on the overpass the week of July 6.
Building it in halves keeps the bridge open. VDOT says a full closure would have cut off interstate access at this exit and pushed traffic onto Route 60 and Route 249. The cost of keeping it open is the two temporary signals, which let one lane of traffic take turns in each direction. The FAQ also explains who gets priority:
- The eastbound and westbound off-ramps get priority, so cars don't back up onto I-64.
- Detection cameras on the ramps watch for queues. Early on, the cameras mistook passing cars for a standing line, and VDOT says adjusting them cut delays.
- VDOT says Route 106 northbound is busiest on weekdays from 7:30 to 8:30 a.m., noon to 2 p.m., and 4 to 6 p.m. At those times the backup can reach a little past the Jimmy Burrell Lane intersection.
That intersection shows up again in the interchange plans.
Spring 2027 Is a Handoff Date
On VDOT's schedule, the bridge's spring 2027 finish lands in the same season the interchange is set to start.
| I-64 Gap Segment A widening | Exit 211 interchange improvement | |
|---|---|---|
| Status on VDOT's page | Under construction | In design |
| Estimated start | Fall 2023 | Spring 2027 |
| Estimated completion | Summer 2027; bridge in spring 2027 | Fall 2029 |
| VDOT cost estimate | $209.5 million | $84 million |
| What drivers see at Exit 211 | One-lane bridge, temporary signals | Rebuilt ramps, new bridge, DDI |
The interchange project is moving forward on paper. VDOT held a location and design public hearing on July 7, 2026. VDOT's procurement listing, last updated in October 2026, shortlists three design-build teams: Allan Myers VA with Rinker Design Associates, Shirley Contracting with Dewberry, and Wagman Heavy Civil with Johnson, Mirmiran & Thompson. The listing does not yet show a final ranking or a contract award.
What Gets Built Once the Bridge Is Finished
The replacement bridge is one half of the finished Route 106 crossing. Richmond BizSense reported in June 2025 that the interchange plan adds a new two-lane bridge next to the replacement. Together the two bridges make that section of Route 106 a four-lane divided road. VDOT's design-build solicitation lists the full scope:
- A four-lane diverging diamond interchange
- Widening of Route 106
- A new bridge over I-64
- Sidewalks
- All four ramps reconstructed and widened
- Drainage, stormwater facilities, traffic signals and lighting
At a diverging diamond, Route 106 traffic briefly crosses to the left side of the road inside the interchange. That turns today's left turns onto the ramps into turns that don't cross oncoming traffic. Each crossover gets a signal that also controls the off-ramp traffic. VDOT has a guide to driving a DDI for anyone who hasn't driven one yet.
The plan also includes a shared-use path on Route 106 from Jimmy Burrell Lane to the roundabout near the county's welcome center, BizSense reported. So the same intersection where the bridge backup ends today becomes one end of a walking and biking connection to the north side of the exit. The north side is where the New Kent Visitors and Commerce Center sits, at 7324 Vineyards Parkway.
A Travel Center Is Waiting on the Interchange
The interchange schedule also sets the timing for one of the county's most talked-about projects. 12 On Your Side reported in September 2026 that Buc-ee's had moved its New Kent opening from 2031 to 2032, and that construction depends on finishing the VDOT project. The station quoted New Kent County Administrator Rodney Hathaway on the amended incentive agreement the Board of Supervisors approved:
"The amendment includes a provision allowing for an extension of up to 18 months if requested in good faith by the Company due to delays in completing related transportation improvements. All parties agree that Buc-ee's should open once the planned traffic improvements are complete in order to avoid gridlock and unsafe traffic conditions."
In the same report, Lindsay Hurt, the county's director of economic development and tourism, said the work includes widening and the diverging diamond at Exit 211, and that transportation is "a big priority" for Buc-ee's. Buc-ee's is putting money into the road as well. BizSense reported in June 2025 that the company agreed to contribute $17.5 million to the interchange. New Kent committed $20 million, and the state's Smart Scale program added $18.2 million.
The Traffic the New Interchange Is Built For
Buc-ee's is planned on the north side of the interchange, and it isn't the only project counting on Exit 211. BizSense listed what is planned on both sides:
- South of the exit: the New Kent City Center industrial park. It already has an 800,000-square-foot AutoZone distribution facility. Target plans a 1.4-million-square-foot distribution center there, and Matan Cos. paid $15 million for nearly 300 acres at the park's north end to build warehouses.
- North of the exit: the Farms of New Kent, a mixed-use development planned for up to 2,500 residential units and 225,000 square feet of commercial space.
"We have so much economic development activity that's happening just south of the interchange," Amy Inman, the county's transportation development director, told BizSense. "There's a lot of pressure for access, accessing that site and those jobs, that we want to be prepared for."
That explains the size of the rebuild. Two-lane Route 106 and a set of ramp signals are what the exit has had to work with. The DDI, the second bridge and four widened ramps are sized for distribution-center trucks, a planned community of up to 2,500 units, and a travel center that has agreed to stay closed until the road can handle it. It also explains the timing. Fall 2029 is when the exit is supposed to be ready for all of that, and the industrial park and the travel center are lining up behind that date.
Getting Through Exit 211 in the Meantime
For about the next three years, the work zone at Exit 211 will change shape more than once. VDOT has named two bypasses for drivers who want to skip it. Take Route 60 to Bottoms Bridge, or Route 249 to Courthouse Road. The bridge FAQ also says the deck demolition can't happen over live traffic, so the job has relied on nightly lane closures on I-64.
Closures and lane shifts are posted on 511Virginia, on the free 511Virginia app, and by dialing 511. VDOT's customer service center at 800-FOR-ROAD, or 800-367-7623, answers questions about the project. The Exit 211 interchange project manager is William Wheeler, and his contact information is on the project page.
If you own a home or land near Talleysville or Roxbury and want to understand what an interchange rebuild running through fall 2029 could mean for your property, I'm happy to walk through it with you. At BERB Real Estate Partners, we look at road projects the way a builder does: what gets built, when, and who it's for. Get your instant home valuation or schedule a consultation with Berb.